Financing

BUDGET AND FINANCING PLAN

 

Infrastructure costs

 

1'420'000.00

   

Trail access

 

 

200'000.00

Total

 

 

1'620'000.00

 

 

 

 

Financing

 

 

Municipality of Monte Carasso

400'000.00

Municipality of Sementina

100'000.00

Municipality of Bellinzona

20'000.00

Municipality of Giubiasco

10'000.00

  

Cantonal Contribution Ltur (Tourism Law)

417'000.00

Schweizer Berghilfe (Swiss Mountain Aid Fund)

 

180'000.00

Vontobel Foundation

 

100'000.00

Regional Agency for Development

 

60'000.00

Banca Raiffeisen

 

31'000.00

Plank Sponsors and  Crowdfunding

ERSBV (Regional Agency for the

Development of Bellinzona and Valleys)

 

60'000.00

Curzutt - S. Barnard Foundation

200'000.00

 

 

 

Total

 

 

1'620'000.00

 

 

 

 

Balance

 

42'000.00

 

 

 

 